Illinois laws

Illinois Prompt Payment Act: Rules and Numbers

Illinois Contractor Prompt Payment Act rules for owners and contractors: 15-day pay deadline, 25-day deemed approval, 10% interest and retainage caps.

Last reviewed October 29, 2026 · General information, not legal advice

General information only, not legal advice. CPA Tax Payroll and Accounting Corp is a CPA firm, not a law firm. Laws change: confirm with the official source or a licensed attorney before you act. Read the full notice.

This page walks through the payment cycle in the Illinois Contractor Prompt Payment Act, from payment application to retainage. The overview explains which jobs are covered, and the checklist and FAQs turn the rules into steps. Retainage and slow payment both tie up cash, so related reading includes our pages on working capital and bank loans and construction and contractors.

What the law requires

RequirementIn plain wordsSection
Owner paysIf the contractor has performed under the contract, the owner pays within 15 calendar days after the owner or its agent approves a payment application.10(1)
Deemed approvalThe application counts as approved 25 days after the owner receives it, unless a written statement of the amount withheld and the reason goes out before then.10(1)
Partial withholdingFor non-conforming work, the owner may withhold only that part's reasonable value and pays for the rest.10(1)
Pay-throughFor accepted work, a contractor pays its subcontractor, and a subcontractor its own, within 15 calendar days after receiving each payment, final payment or retainage.10(2)
SuspensionAn unpaid contractor or subcontractor may suspend work without breach penalty after 7 calendar days' written notice.15(b)
Retainage capNo more than 10% of each payment before the contract is 50% complete, and no more than 5% held from then on.20

Key numbers and dates

ItemAmount or dateYear in forceSource label
Owner pays after approvalWithin 15 calendar days2026CPPA 10(1)
Deemed approval25 days after receipt, unless a written withholding statement goes out first2026CPPA 10(1)
Pay-through to subcontractors15 calendar days after receipt2026CPPA 10(2)
Interest on late payment10% per year2026CPPA 15(a)
Notice before suspending work7 calendar days, in writing2026CPPA 15(b)
Retainage cap10% of each payment before 50% complete; 5% from then on2026 (Section 20 changed 2019)CPPA 20
Days in the Illinois payment cycle calendar days under the Act, law in force 2026
Deemed approval if owner is silent25 days
Owner pays after approval15 days
Contractor pays sub after receipt15 days
Written notice before suspending work7 days

Source: 815 ILCS 603/10 and 603/15

Recent and pending changes

No amendment after Public Act 101-432, effective August 20, 2019, appears in the source notes of the text read on October 27, 2026.

Penalties and enforcement

The Act names no agency and has no fine or criminal penalty. The remedies are the unpaid amount, interest and the right to stop work. Lien rights come from a different law, the Mechanics Lien Act, which this page does not cover. A lender's claim on business assets is another matter again; see the Illinois UCC.

TierWhat followsSection
Late paymentThe delinquent party owes the payment plus 10% interest per year15(a)
Overlap with lien interestNot duplicated with Mechanics Lien Act interest15(c)
Still unpaidWork may be suspended after 7 calendar days' written notice, until paid15(b)
Retainage above the capA contract may not permit holding back more than Section 20 allows20

Official sources